The Site Installation Plan (SIP) is a mandatory document that lists all the information vital to the smooth running and safety of a worksite. But what should this document include? Distribution networks, storage areas, living quarters, traffic flows, fences: find out everything you need to know about a site installation plan.
The Site Installation Plan (SIP) is a graphical document that brings together all the information needed to set up and lay out a worksite. It is drawn up by the company in charge of structural work.
From a legal standpoint, the PIC is essential: it enables us toto obtain the administrative authorizations required for the installation of the work, particularly in terms of safety. For example, this is necessary in order to safely install various pieces of construction equipment in a public space.
The PIC specifies the exact location of fixed equipment and components present when work is being carried out:
The site installation plan also makes it possible to ensure the proper organization of the worksite by optimizing the layout of the various zones within the available space. A properly planned worksite avoids complications, delays and additional costswhile improving on-site working conditions.
Please note that the PIC information is supplemented by other documents:
With job site activity management software such as Techtime, you can easily . share the site installation plan with everyone involved. Via a web application or a mobile applicationeveryone has quick and easy access to all the information they need to get the job done right.
The site installation plan must contain as much information about the site as possible. Here are a few essential items to include on the SOP.
The background plan forms the basis of the SOP. It is divided into two types of plan:
Another important element: the site installation plan must show distribution networks and energy connections: drinking water These include drinking water, wastewater, electricity, gas, Internet and telephony.
Identifying these networks enables you to apply for the necessary authorizations from the various suppliers and distributors well in advance. But also to avoid damaging them during construction.
On an ICP, the living quarters correspond to all the areas allocated to the reception of workers on the siteand their layout rules. These include :
It should be noted that these areas must be covered, connected by circulation spaces and not be located in an overflight zone for lifting equipment. The living quarters are generally located at the site entrance.

For each element, it is necessary to indicate the nature of the material, the available surface and the type of protection used (geotextile, concrete, etc.). Certain locations must also be indicated on the PIC:
It is compulsory to show on the PIC the locations and heights of all lifting equipment, such as cranes such as cranes, forklifts and freight elevators.
The PIC must indicate the altitude and height of all installations including :
The site installation plan must indicate the traffic flows between the different zones. For the safety of workers, these paths must be laid out and secured.
It is also necessary to show traffic routes for site vehicles - in compliance with the Highway Code - as well as parking areas and evacuation points.
If necessary, you can install traffic lights and crosswalks to ensure safe traffic flow for pedestrians and drivers.
For safety reasons and to prevent theft, the site must be completely closed to the public. This means mentioning all types of fencing on the PIC:
Sustainable development and respect for the environment are issues that are increasingly present on construction sites. It is therefore important to show on the PIC all the means put in place to to protect the environment :