Please note: this article refers to French regulations and standards.
The final statement of account (DGD, décompte général définitif) is an essential document in the handover of works in France. In particular, it establishes the parties’ payment entitlements. How it works, what it contains, how it is drawn up, the roles of the parties, appeals, tacit DGD: here is everything you need to know about the final statement of account.
In brief
The final statement of account (DGD) closes a worksite financially and legally: it validates the amount of the works, triggers payment of the balance, sets entitlement to late-payment interest and starts the period for disputes. It brings together the draft final statement, the balance payment certificate and the summary of interim payments. The contractor, the project manager and the client each have 30 days at their stage. In the event of disagreement, the contractor sends a statement of claim. Since 2014, a tacit DGD has been possible.
What is a DGD?
The final statement of account, or DGD, is the document that closes a worksite, both financially and legally. It serves several purposes:
- it validates the amount of the works and triggers payment of the balances within a period governed by the general administrative conditions (CCAG);
- it sets entitlement to late-payment interest, i.e. an automatic percentage increase if payment deadlines are not met;
- it marks the start of the period for disputes.
The DGD must therefore follow a specific procedure, since it can end the financial relationship between all the parties.
The final statement of account must be sent to the building damage insurer: it states the final amount of the worksite and avoids possible disputes about the guarantee. After the handover, the DGD is the official basis for any dispute over the amounts stated.
What does the DGD contain?
The final statement of account is made up of three separate documents:
- The draft final statement: drawn up by the contractor (see below), it lists all the work actually carried out and the total amount due, excluding VAT.
- The balance payment certificate: it is based on the difference between the total of the draft final statement and the last statement submitted by the contractor.
- The summary of interim payments: it lists the monthly statements paid to the contractor, with the payment dates and the balance outstanding. This document sets the amount of the final statement of account.
Work carried out and total amount excl. VAT
Difference from the last statement
Payments, dates and balance outstanding
Who draws up the DGD?
A worksite’s DGD concerns three parties involved in the works:
- the contractor;
- the client;
- the project manager.
The final statement of account is drawn up in several stages:
- the handover of works is recorded in a report by the project manager, together with the holder of the works contract;
- on the basis of the report, the contractor draws up a draft final statement, sent to the client and the project manager;
- after receiving the draft, the project manager must draw up the general statement within 30 days, then send it to the client;
- the client also has 30 days to notify this statement to the contractor;
- in turn, the contractor must respond to the statement within 30 days.
At the end of this last stage, the final statement of account is officially established.
- 1HandoverReport by the project manager
- 2Draft final statementDrawn up by the contractor
- 3General statementProject manager: 30 days
- 4NotificationClient: 30 days
- 5AcceptanceContractor: 30 days
What happens if there are reservations about the DGD?
If the DGD drawn up by the project manager is accepted and signed by the contractor, the document becomes final and payment of the balance must be triggered within 30 days.
However, the contractor may disagree with the general statement and not approve it. In that case, they must send a statement of claim to the project manager and the client.
In it, the contractor must specify the amounts claimed, the necessary supporting documents and the basis for calculating the sums claimed. These claims are examined and, if accepted, trigger payment of the undisputed sums within 30 days.
If this amicable procedure fails, the contractor has 6 months to refer the matter to the competent administrative court, which will then set the balance of each party’s contractual obligations.
What is a tacit DGD?
Since 2014, an amendment to the CCAG for works has allowed a so-called tacit procedure for the final statement of account. It is not unusual for the project manager to delay drawing up the DGD when there are reservations at handover. To prevent this practice, the tacit DGD speeds up payment of the sums due to the contractor.
So if the draft final statement goes unanswered for 30 days, the contractor can notify a draft general statement consisting of:
- the draft final statement;
- the draft balance statement;
- a summary of the balance and monthly interim payments.
On receipt of these documents, the project manager then has 10 days to draw up the DGD. If there is no response within this period, the draft statement becomes the official DGD.
Frequently asked questions
What is a worksite DGD?
The final statement of account is the document that closes a worksite, both financially and legally. It validates the amount of the works and triggers payment of the balance.
What are the DGD deadlines?
The project manager has 30 days to draw up the general statement after receiving the draft final statement, the client 30 days to notify it and the contractor 30 days to accept it. The balance is then paid within 30 days.
What is a tacit DGD?
Since 2014, if the draft final statement goes unanswered for 30 days, the contractor can notify a draft general statement. If the project manager does not respond within 10 days, this draft becomes the official DGD.