Please note: this article refers to French regulations and standards.
In construction, several companies often carry out work on the same site. This simultaneous activity can lead to more risks and accidents on a worksite. To analyse and prevent all risks and ensure workers’ safety, companies can draw up a prevention plan. How it works, what it is for, how to draft and communicate it, obligations: find out everything you need to know about the worksite prevention plan.
In brief
The worksite prevention plan prevents interference risks when a contractor works on a host company’s premises. Drafted jointly after a joint inspection before the works, it defines the scope of the interventions, identifies hazards and sets out prevention measures, instructions, first aid and the chain of command. It must be drawn up in writing for the hazardous work listed in the decree of 19 March 1993 and whenever the intervention reaches 400 hours over 12 months.
What is a worksite prevention plan?
The worksite prevention plan is a document designed to prevent the risks linked to a contractor (EE) working within a host company (EU), in its outbuildings or on its worksites.
These risks can arise from interference between the activities, installations or equipment of the two companies in the same place. The prevention plan therefore makes it possible to identify and formalise the additional risks – known as interference risks – caused by this co-activity. The document sets out the prevention measures to be associated with each interference risk between the two activities.
- Its premises, outbuildings or worksites
- Shows access and traffic routes
- Takes part in the joint inspection
- Its employees, its equipment
- Clearly defined interventions
- Applies the prevention measures
How do you draw up a worksite prevention plan?
The worksite prevention plan must be drawn up jointly by the two companies and is used, among other things, to:
- define the scope of the contractor’s interventions;
- identify potential hazards;
- show the contractor’s employees the access and traffic routes to the host company’s installations.
The rules applicable to the prevention plan are set out in the French Labour Code. The joint inspection must be carried out before the works begin, whatever the circumstances – for example, even if the contractor already knows the site.
The worksite prevention plan must be available at all times to:
- the labour inspectorate;
- the occupational doctors of both companies;
- prevention officers from social security bodies;
- representatives of the construction industry’s professional prevention body (OPPBTP);
- the social and economic committees (CSE).
What should a worksite prevention plan contain?
The content of a worksite prevention plan may vary according to the nature of the activities and works to be carried out, the number of companies involved and the prevention measures the companies consider necessary.
However, certain items must always appear in the prevention plan:
- a description of the hazardous activities and the corresponding means of prevention;
- the suitability of the equipment, devices and installations for the operations to be carried out, and how they are maintained;
- the instructions to be given to workers;
- the organisation of first aid in an emergency and a description of the arrangements;
- the conditions under which employees take part in the various works and the organisation of the chain of command.
Alongside this information, other documents are appended to the worksite prevention plan, namely:
- the list of posts held by workers who require enhanced individual medical monitoring because of the risks linked to work at the host company;
- the identification of asbestos-containing materials or asbestos survey reports.
Prevention plan: when must it be in writing?
A prevention plan is required whenever a contractor works on site. Under the French Labour Code, it must be drawn up in writing in two situations.
First, if the works involve risks identified in the decree of 19 March 1993. This covers in particular works:
- involving exposure to ionising radiation;
- involving exposure to explosive, flammable, toxic, harmful, carcinogenic, mutagenic substances and preparations, etc.;
- involving maintenance on installations at very high or very low temperatures;
- exposing workers to the risk of falling from a height of more than 3 metres;
- involving a risk of drowning;
- involving a risk of burial, etc.
Ionising
Explosive, toxic, carcinogenic…
More than 3 metres
Risks identified by the decree
The worksite prevention plan must also be drawn up in writing when the works carried out by the contractor amount to a total of at least 400 working hours over a period of 12 months or less.
For simpler management of your worksite and job activities, discover Techtime. Through a web app or a mobile app, you can easily manage your worksites, organise jobs and centralise all your essential documents, such as the worksite prevention plan.
Frequently asked questions
When must the prevention plan be in writing?
In two cases: when the works involve risks listed in the decree of 19 March 1993 (ionising radiation, hazardous substances, falls of more than 3 metres, drowning, burial…) and when the contractor’s intervention totals at least 400 hours over 12 months.
Who drafts the prevention plan?
The host company and the contractor, jointly, after a joint inspection that must be carried out before the works begin.
What does a prevention plan contain?
Hazardous activities and their means of prevention, the suitability of equipment and installations, instructions to workers, the organisation of first aid and the chain of command, with the posts requiring enhanced monitoring and the asbestos survey appended.