Introduction
The handover of works is a very important stage in a construction project. It marks the end of the worksite, of course, but above all it lets you assert your rights under the guarantees. Whether for building a house or new home, or for a renovation, the handover is the step before moving in and lets the person who commissioned the work officially approve it.
In this article, we look at the legal aspects of the handover of works under French law, the purpose of the handover report, its legal framework and the options for claims under the guarantees.
In brief
The handover of works marks the end of the worksite: the client accepts the works, with or without snags (Article 1792-6 of the French Civil Code). Its date starts the guarantees running: completion, proper functioning and ten-year. It can be express (report signed by mutual agreement), tacit (taking possession and paying) or judicial. During the inspection, check every point against the contract and note defects in the report, dated and signed by all parties. Once the snags have been cleared, file the DAACT (completion and compliance declaration) with the town hall.
The handover of works: a step not to be overlooked
Organising the handover
The handover is generally organised by the builder. However, for a renovation for example, you may have hired several trades yourself (plumber, electrician, tiler, etc.). You can then bring them together for an overall handover meeting or call each tradesperson separately. In any case, it is essential that all the stakeholders are present.
Why the handover matters

The handover is an important phase of your construction project. It gives you the right to a one-year period to have the defects or faults found repaired. These must then be recorded in the handover report. If defects are found later, you will have to report them by registered letter and set a deadline for the work.
You need to be careful, because the handover amounts to accepting that the work complies. A detailed review of the work carried out is therefore essential. If the report proves incomplete or incorrect, you could have difficulty asserting your rights and enforcing the guarantees in the event of defects.
More precisely, the handover date is the starting point for the following guarantees: completion guarantee, proper functioning guarantee, two-year guarantee, ten-year guarantee and building damage insurance.
The different forms of handover
There are 3 types of handover: express handover, tacit handover and judicial handover.
Express handover
Express handover is the most common procedure and is amicable. The client and the contractor or contractors inspect the worksite together and sign the report, with or without snags.
Tacit handover
A handover is considered tacit when it has not taken place formally, i.e. if no claim has been made, if the owner has already taken possession of the structure or if they have already paid for the work in full.
Taking possession of the structure and paying for the work thus means that the client tacitly and unequivocally accepts the structure as it is, without any snags.
Judicial handover
A judicial handover must take place when there is a disagreement between you and the construction company and no amicable agreement has been reached. A judge then decides whether to pronounce the handover or order the tradesperson to carry out a number of repairs.
Joint inspection and signed report, with or without snags
Taking possession and paying in full
Pronounced by a judge in the event of disagreement
How does a handover take place?
A handover without snags
You find no defects during your inspection? Then you can state in the report that the handover took place without snags and that you accept the work. You will then have to pay the outstanding balance, either immediately after the handover if you are assisted by a professional, or within 8 days of receiving the keys.
A handover with defects found

You find defects, unfinished or non-compliant work? Then you must record them in the report as visible defects.
You can then refuse the handover and schedule a new handover date with the company.
If you have no choice but to move in immediately, you must state in the report that moving in does not mean acceptance of the works.
Alternatively, you can accept the work but with snags.
You then simply list all the problems found, state the deadline by which they must be fixed and notify the company by registered letter with acknowledgement of receipt.
The declaration of completion
All the snags finally cleared? Now it is time to declare that the construction or fit-out work is complete. The DAACT (declaration certifying completion and compliance of the works) must then be filed with the town hall to certify that the works comply with the building permit or prior declaration. This administrative document must be sent to the town hall no later than 30 days after the end of the works.
What checks should you carry out at handover?
The quality of the work
At handover, you must check that the work matches what was agreed with the contractor. It is important to examine every detail thoroughly and make sure all the equipment works, including taps, electrical installations, etc. For this stage, you can perfectly well be accompanied by a construction expert, who then takes on responsibility.
The checkpoints
If problems are found at any of the checkpoints, they must be recorded in the handover report. So as not to forget any, you can refer to your works contract, which should list all the compliance criteria.
All materials, equipment and installations must be checked: surfaces, type of materials, electricity, heating, water, ventilation, joinery.
The handover report
What format for the handover report?
It is strongly recommended to formalise the handover of your works in a written document: the handover report. You can record all your comments in it, which will give you a basis for any claims. Although it is not legally mandatory, your report will be an essential document if you need to assert your rights or in the event of a dispute with your contractor. The handover report must be dated and signed by all the stakeholders, each of whom should receive a copy.
What the handover report contains

Here are the items to include in your report:
- Identity of each party
- Date of handover
- Worksite address
- Any snags
- Detailed description of each defect found
- Deadline for remedying (agreed with the contractor)
- Signatures of the parties
Conclusion
Remember that under Article 1792-6 of the French Civil Code, the handover of works marks the end of the worksite and the moment when the client can accept the works, with or without snags. The report is the document in which all the defects found are recorded. It must be signed by all parties: the client and everyone who carried out the work.
Frequently asked questions
What is the difference between a handover with and without snags?
Without snags, you accept the work as it is and pay the balance. With snags, you accept the work but list in the report the defects to be corrected and the deadline given, notified to the company by registered letter.
Is the handover report mandatory?
It is not legally mandatory but strongly recommended: dated and signed by all parties, it serves as a basis for asserting your rights and guarantees in the event of a dispute.
What is a tacit handover?
A handover that has not taken place formally: the client has taken possession of the structure and paid for the work, which amounts to acceptance without snags.