Please note: this article refers to French regulations and standards.
According to INSEE (Franceâs statistics office), construction production costs rose by 0.4% between the first and second quarters of 2024. Generally speaking, indices across all construction sectors have kept rising since 2021. While energy prices seem to have been falling since early 2023, the same is not true of raw materials (source). In these conditions, how can you apply a construction price revision to quotes or invoices to keep contracts profitable?
In brief
Price revision lets you adjust the price of a construction contract to economic fluctuations during the works, using the BT (building) and TP (public works) indices published by INSEE. It differs from price updating, which is applied once before the works start. Revision is required in particular for contracts lasting more than three months or involving large quantities of supplies. Without a reference index, the client uses a parametric formula.
1Why update your prices in construction?
Price revision in construction lets you adjust construction costs in line with economic fluctuations during your contract. These changes concern raw materials as much as labour. Such updates only apply to a revisable-price contract, not a fixed-price one (which can nevertheless be subject to price updating) (source).
It is best to plan this revision for long construction projects. The benefits are as follows:
- You protect yourself against rising construction costs by passing them on in your new quotes or invoices. You secure a more profitable worksite despite the circumstances.
- You avoid unexpected financial difficulties, both on your side and on your clientâs. The economic stability of your projects increases your customersâ confidence.
- Taking the real costs of a worksite into account balances the market and encourages healthier competition between construction tradespeople. This is particularly the case for public contracts. The French Public Procurement Code (CCP) cannot impose a fair redistribution of payment to subcontractors. However, decree no. 2022-1683 of 28 December 2022 sets a minimum advance paid to the contract holder and its SME subcontractors (source).
2What are INSEEâs price revision indices for?
In INSEEâs database, an index value is the value of a product or service over a given period. For construction, it is updated monthly. However, the institute takes three months to calculate a price revision. That is why it provides a provisional index (IP), so as not to delay the revaluation of the service, until it publishes a final index (ID) (source).
An index series groups several index values for a given activity, specifying their publication in the Journal Officiel (Franceâs official gazette). INSEE distinguishes the Building Index (BT) from the Public Works Index (TP) (source).
- The first index covers construction and building renovation projects, grouping 54 specialities such as carpentry, joinery, painting and electrical work.
- The second index covers contractors working on public infrastructure projects and urban development (roads, bridges, tunnels, pipelines, etc.). Some indices are broken down into sub-categories such as civil engineering or underground works.
The index series share the same index values to revalue the prices of quotes or ongoing contracts. A single value combines wages, charges, the prices of materials, energy, transport equipment and other miscellaneous costs. However, the TP index also takes into account the index for worksite waste. The aim is to keep pricing consistent throughout the worksite while minimising losses for building contractors (source).
3Construction price revision or updating: what are the differences?
Revision and updating are synonyms in everyday language. In construction, however, the two procedures differ in how they are carried out and calculated.
Specific periods for updating prices
Price updating is carried out once, before the works start. It is best applied if the worksite is short, so as not to be affected by cost changes. The time between setting the initial price and the actual start of works must be more than 3 months. Its formula and terms are set out in the CCAP (special administrative clauses) or the CCAG (general administrative clauses).
Price revision can be carried out at any time during the works. Its terms are also set out in the clauses mentioned above, based on the BT indices for the month in which the price was submitted. Price revision clauses are freely negotiable in private contracts. However, they are mandatory in public contracts in the following cases, under Article R2112-14 of the French Public Procurement Code:
- The contract performance period is longer than three months.
- The contract requires large quantities of supplies.
- The price of supplies, such as raw materials, depends on fluctuations in world prices. A price revision clause is needed to refer to the official indices set by Article R2112-13 of the same Code.
Different formulas for working out the price adjustment
The construction price revision formula differs from the updating formula because they are not based on the same timeframes. BTa is the BT index with a given value âaâ that depends on the building sector. P is the adjusted or revised price, while P0 is the initial cost.
When BTa has the index (m0), its value corresponds to the date the works started. When the BT index is (m â 3), its value corresponds to the date of the offer, i.e. three months before the works started.
| Updating formula | Revision formula |
|---|---|
| P = P0 Ă BTa(m â 3) / BTa (m0) | P = P0 Ă BTa / BTa (m0) |
- For short worksites
- P = P0 Ă BTa (m â 3) / BTa (m0)
- Contracts over three months or with a large share of supplies
- P = P0 Ă BTa / BTa (m0)
4How do you revise prices in construction without a reference index?
Some worksite tasks have no index value or BT or TP index series on INSEEâs website. These may include demolition, landscaping, general maintenance or tasks involving new technologies (3D printing, robotics, BIM). These works may have other indices, such as EV (green spaces) or ING (engineering).
In this case, the client applies a parametric formula to revise or update the worksite price. To do so, they break down the overall estimate of the work into simpler items with costs that can be linked to existing indices. The BT01 âall tradesâ index can be used by default.
Price revision in construction only applies to revisable prices and to long worksites. Keep a close eye on the cost indices available on INSEEâs website, split between the BT and TP series. Be careful to distinguish provisional indices from final ones, as the institute takes a few months to update its data. The revision or updating terms must appear in the CCAP or CCAG. To make updating your documents easier, consider the worksite electronic document management (EDM) in our Techtime app.
Frequently asked questions
What is the difference between price revision and price updating?
Updating is carried out once, before the works start. Revision can take place at any time during the works, according to the terms set in the contract.
When should you plan a price revision?
In particular when the contract lasts more than three months, requires large quantities of supplies or when raw material prices depend on world prices.
How do you revise a price without a reference index?
When some works have no BT or TP index, the client applies a parametric formula, breaking the price down into its different cost items.