In its monthly business survey of the building industry, INSEE (France’s statistics office) notes a return to normal for the balance of opinion on expected prices. After peaking at 60% in 2022, this means construction companies are considering lowering their selling prices (source). This drop is linked to weak demand or falling costs. So, to avoid working at a loss, there is an indicator that helps strike the right balance between selling price and sufficient margins. It involves calculating direct costs (déboursé sec), an essential step to calculate worksite prices and margins.
In brief
Direct costs cover a worksite’s direct expenses: materials, labour and equipment. Example: for a 10 m × 2.5 m breeze-block wall, they amount to €527.50 of materials, €600 of labour and €50 of equipment, i.e. €1,177.50. You then obtain the cost price by applying the overheads coefficient (€1,354.10 with 1.15), then the pre-tax selling price by applying the margin rate (€1,624.92 with 1.20), before adding VAT.
1Calculate direct costs first
Direct costs (DS) let you price your worksite and assess its profitability. The aim is to find a competitive, realistic selling price that lets you make a profit.
What is the definition of direct costs?
Direct costs cover the direct expenses needed to carry out a construction project. These costs fall into three categories:
- Purchasing materials or supplies. For each type of raw material, multiply the quantity by the unit price.
- Labour costs. These cover both your employees and subcontractors. Each construction trade has its own hourly rate or a price that depends on the area to be worked (source).
- Hiring worksite equipment, depending on how long it is needed.
Direct costs take into account neither the margin to be earned nor the company’s fixed costs (rent, electricity, IT equipment, etc.). Other contingencies are not included either, such as extra handling time or supplies lost through negligence or theft on worksites (source).
How do you calculate direct costs?
The direct costs of a piece of work are calculated using the following formula:
Direct costs = labour cost + cost of supplies + cost of equipment
Imagine a bricklayer wants to build a breeze-block wall 10 m long, 2.5 m high and 20 cm thick. The direct cost calculation breaks down as follows.
a) Purchasing materials
To build this wall, you need 250 standard 25 cm × 50 cm blocks, for a total area of 25 m². The volume of mortar needed to assemble these masonry units is 1,250 L, i.e. 50 litres of mortar per m² of wall. Finally, steel ties are needed to reinforce the wall. With two rows of reinforcement of 10 metres each, we get 20 m.
If the unit prices are as follows (€1.50 per block; €90 per m³ of mortar; €2 per m of reinforcement), we get the following result:
Cost of materials = 250 × 1.5 + 1.25 × 90 + 20 × 2 = 375 + 112.5 + 40 = €527.50
b) Labour cost
A bricklayer’s hourly rate in France ranges from €35 to €65 excluding VAT. If your tradespeople cost you €40 an hour and it takes them about 15 hours to build this wall, you can work out the following:
Labour cost = 40 × 15 = €600
c) Cost of equipment
Whether your equipment is hired or your own, you can allow around €50 to cover wear and tear on tools, consumables and small equipment.
In the end, your total direct costs will be: 527.5 + 600 + 50 = €1,177.50.
2Calculate the pre-tax selling price from your direct costs
Direct costs alone are not enough to set the pre-tax selling price of your service. To do so, you need to add certain parameters specific to your company, such as overheads or the cost of contingencies like bad weather (source).
Calculating the cost price from the company’s overheads
Overheads are your company’s costs that are not directly linked to the worksite. As indirect expenses, they belong to class 6 accounts in the French chart of accounts. They fall into two categories (source):
- Fixed costs. These expenses are paid every month or every year, regardless of activity. They mainly include the rent for your premises, professional insurance, administrative salaries, depreciation, etc.
- Variable costs. These vary with the company’s activity. They can include mileage expenses, energy bills, bonuses, communication bills (telephone, internet), bank charges, etc.
All these items are combined in a single formula to define the overheads coefficient (FG). It depends on the construction trade, as some tradespeople have greater needs than others (for example, a joiner needs a workshop). It is always calculated on the basis of your previous financial year:
Overheads coefficient = 1 + (annual overheads + non-productive staff costs) / (annual cost of materials + site staff costs)
From this coefficient, you determine the cost price (PR) of your worksites. In our example above, if our bricklayer has an FG coefficient of 15%, his cost price will be:
Worksite cost price = 1,177.5 × 1.15 = €1,354.10
Calculating the selling price from the margin rate
The margin rate is a coefficient applied to the cost price. It lets the company achieve a certain profitability on its service while taking into account contingencies that may disrupt the worksite. Unlike the mark-down rate, calculated from the selling price, the margin rate is based on the purchase cost of the work.
It varies between building professionals, but most apply a rate of between 20 and 25%. To obtain the pre-tax selling price of your worksite service, multiply the cost price by this coefficient. With a margin rate of 20%:
Pre-tax selling price = 1,354.1 × 1.20 = €1,624.92
The price of the service including VAT is obtained by adding VAT (in France: 20% for new build, 10% for renovation, 5.5% for energy improvements; source). If the tradesperson has to carry out ancillary or highly specific services, they can set several overheads coefficients and margin rates. The same applies if work is subcontracted.
- 1Direct costs1 177,5 €
- 2Cost price× 1.15 overheads = €1,354.10
- 3Pre-tax selling price× 1.20 margin = €1,624.92
- 4Price incl. VAT+ VAT at 20, 10 or 5.5% (France)
3Optimise your worksite’s profitability with a few tips
To avoid wasting time pricing the worksite by hand, refer to price libraries such as Batichiffrage or Batiprix. Their research departments set average rates for the cost of supplies and labour, as well as working time.
If you want to increase margins while remaining competitive, you have two options:
- either revise the selling price of your work, while keeping the increase in check so as not to drive customers away;
- or negotiate the purchase price or discounts on your materials, keeping an eye on the costs of inflation. Don’t hesitate to put new suppliers in competition, without compromising the quality of your raw materials.
Beyond calculating direct costs to draw up a fair construction quote , don’t neglect the following tasks:
- Plan your worksite early and flexibly, to leave enough margin for contingencies or quality inspections.
- Track your worksite in real time. By improving communication between your teams, you save considerable time and increase productivity.
The worksite tracking software Techtime offers all these features, and more, to maximise the profitability of your worksites. Discover its mobile version now.
Direct costs equal the sum of materials purchases, labour costs and the cost of worksite equipment. They are only part of the selling price of the work. To set that price, you need to add the overheads coefficient and the margin rate. The VAT rate, which in France depends on the type of worksite (new build or renovation), gives you the price of the service including VAT.
Frequently asked questions
What are direct costs?
The direct expenses needed to carry out a worksite: purchasing materials, labour costs and equipment. They include neither the margin nor the company’s fixed costs.
How do you calculate direct costs?
Direct costs = labour cost + cost of supplies + cost of equipment. For a 25 m² breeze-block wall: €600 + €527.50 + €50 = €1,177.50.
How do you go from direct costs to the selling price?
Multiply direct costs by the overheads coefficient to get the cost price, then by the margin rate to get the pre-tax selling price, and add VAT (in France, 20, 10 or 5.5% depending on the works).